Outdoor Skating Rink and building Project

Proposed Rink and Building location

Guide of Community Led Building Process: Click here

Roadmap of City Process: Click here

Phase 1: Outdoor rink

Estimated Cost: $412,000 with concrete base, $202,000 without base (grass)

Raised To Date:

  • 100,000 City of Edmonton CLIP Grant

  • $25,000 City of Edmonton Planning Grant

  • $27,000 Community League Fundraising

  • $50,000 Cameron Heights Home Owners' Association Donation

$210,000 left to be fundraised with concrete base

$0 left to be fundraised without concrete base

Where we are at:

Strategy Phase

  1. Strategy Documents Submitted to City of Edmonton - May 13, 2019

  2. Recieved Strategy Approval - July 4, 2019

Concept Phase

  1. Complete business case - Completed Feb 24, 2020

  2. Hire Architect to complete functional program and concept/Pre-Design Drawings, Detailed Project and Operating Budget - Hired on Holo Blok Architects to complete the masterplan for the site on Oct 31, 2019.

  3. Hired Global Sport Resources to complete Rink Drawings in September 2019.

  4. Submit business case and appendicies to City - March 13, 2020

  5. Sign Municipal Improvement Agreement with City - July 16, 2020

  6. Recieve Concept Phase Approval - COMPLETED - June 24, 2020

  7. Continue Fundrasing - ONGOING

Design Phase

  1. Develop Design Drawing Reports - COMPLETED

  2. Apply for Development Permit from City - APPROVED JUNE 9, 2020

  3. Construction Drawings - APPROVED

  4. Electrical Permit Applications - IN PROGRESS

  5. Utility Coordination - COMPLETED

Build Phase

  1. Contractor start up meeting with City - July 3, 2020

  2. Pre-construction inspection at site by the City - July 3, 2020

  3. Construction begins - AUG 4, 2020 (weather dependant)

  4. Construction ends - EXPECTED 4 WEEKS (weather dependant)

  5. Construction Completion Certificate Received by the City

Operate Phase

  1. Insure the new structure - SEPTEMBER 2020

  2. Final Funding Reconciliations SEPTEMBER 2020

  3. Plan a celebration and opening event - SEPTEMBER 2020




Phase 2: multipurpose building

Estimated Cost: 1.2 Million

Raised To Date:

  • $25,000 Community League Fundraising

  • $400,000 City of Edmonton CLIP Grant

  • $25,000 City of Edmonton Planning Grant

To be fundraised:

  • $425,000 CFEP Grant - Applied June 2020

  • $750,000 to be fundraised

Where we are at:

Strategy Phase

  1. Strategy Documents Submitted to City of Edmonton - May 13, 2019

  2. Received Strategy Approval - July 4, 2019

Concept Phase

  1. Complete business case - Completed Feb 24, 2020

  2. Hire Architect to complete functional program and concept/Pre-Design Drawings, Detailed Project and Operating Budget - Hired on Holo Blok Architects to complete the masterplan for the site on Oct 31, 2019.

  3. Submit business case and appendices to City - March 13, 2020

  4. Sign Municipal Improvement Agreement with City - COMPLETED SEPT 2020

  5. Receive Concept Phase Approval - AWAITING

  6. Continue Fundraising - ONGOING

Design Phase

  1. Develop Design Drawing Reports - SEPT-NOV 2020

  2. Apply for Development Permit from City -

  3. Design Construction Drawings

  4. Apply for Building Permit Application

  5. Utility Coordination -

  6. Continue Fundraising -

Build Phase

  1. Tender Documents -

  2. Construction Contract -

  3. Transition to Operate Plan

  4. Substantial Completion Certificate

  5. Operation and Maintenance Manuals

  6. As Built and Record Drawings

  7. Occupancy Permit

  8. Construction Completion Certificate

Operate Phase

  1. Execution of Agreements

  2. Final Funding Reconciliations

  3. Grand Opening