Outdoor Skating Rink and building Project
Proposed Rink and Building location
Guide of Community Led Building Process: Click here
Roadmap of City Process: Click here
Phase 1: Outdoor rink
Estimated Cost: $422,000 with concrete base, $202,000 without base (grass)
Raised To Date:
100,000 City of Edmonton CLIP Grant
$25,000 City of Edmonton Planning Grant
$27,000 Community League Fundraising
$50,000 Cameron Heights Home Owners' Association Donation
$220,000 left to be fundraised with concrete base
$0 left to be fundraised without concrete base
Where we are at:
Strategy Phase
Strategy Documents Submitted to City of Edmonton - May 13, 2019
Recieved Strategy Approval - July 4, 2019
Concept Phase
Complete business case - Completed Feb 24, 2020
Hire Architect to complete functional program and concept/Pre-Design Drawings, Detailed Project and Operating Budget - Hired on Holo Blok Architects to complete the masterplan for the site on Oct 31, 2019.
Hired Global Sport Resources to complete Rink Drawings in September 2019.
Submit business case and appendicies to City - March 13, 2020
Sign Municipal Improvement Agreement with City - July 16, 2020
Recieve Concept Phase Approval - COMPLETED - June 24, 2020
Continue Fundrasing - ONGOING
Design Phase
Develop Design Drawing Reports - COMPLETED
Apply for Development Permit from City - APPROVED JUNE 9, 2020
Construction Drawings - APPROVED
Electrical Permit Applications - IN PROGRESS
Utility Coordination - COMPLETED
Build Phase
Contractor start up meeting with City - July 3, 2020
Pre-construction inspection at site by the City - July 3, 2020
Construction begins - AUG 4, 2020 (weather dependant)
Construction ends - COMPLETED (weather dependant)
Construction Completion Certificate Received by the City
Operate Phase
Insure the new structure - SEPTEMBER 2020
Final Funding Reconciliations SEPTEMBER 2020
Plan a celebration and opening event - DECEMBER 2020
Restart process for Phase 2 - Concrete Base - ONGOING
Phase 2: multipurpose building
Estimated Cost: 1.4 Million
Raised To Date:
$125,000 Community League Fundraising
$400,000 City of Edmonton CLIP Grant
$25,000 City of Edmonton Planning Grant
$150,000 to be loaned
To be fundraised:
$700,000 CFEP Grant - Application sent June 15 2021
Where we are at:
Strategy Phase
Strategy Documents Submitted to City of Edmonton - May 13, 2019
Received Strategy Approval - July 4, 2019
Concept Phase
Complete business case - Completed Feb 24, 2020
Hire Architect to complete functional program and concept/Pre-Design Drawings, Detailed Project and Operating Budget - Hired on Holo Blok Architects to complete the masterplan for the site on Oct 31, 2019.
Submit business case and appendices to City - March 13, 2020
Sign Municipal Improvement Agreement with City - COMPLETED SEPT 2020
Receive Concept Phase Approval - COMPLETED NOV 2020
Continue Fundraising - ONGOING
Design Phase
Develop Design Drawing Reports - JUNE 2021
Apply for Development Permit from City -
Design Construction Drawings
Apply for Building Permit Application
Utility Coordination -
Continue Fundraising -
Build Phase
Tender Documents -
Construction Contract -
Transition to Operate Plan
Substantial Completion Certificate
Operation and Maintenance Manuals
As Built and Record Drawings
Occupancy Permit
Construction Completion Certificate
Operate Phase
Execution of Agreements
Final Funding Reconciliations
Grand Opening